Building Case Study 4 - Hospital: Mid-Kent Oncology Centre, Maidstone
Roger Burr (Powell Moya Partnership) , Andrew Mason (Powell Moya Partnership) , Jeremy Leyer (Landscape Architect) , Chris Baxter (R.W. Gregory) , Ian Menzies (Charles Weiss Partnership) , Gerald Stone (AYH Health) , Anthony Field (AYH Partnership) & Wendy Pitts (J. Mowlem Construction)



1


General View

©Powell Moya Partnership


RB: We're gathered here as a group to discuss the Mid-Kent Oncology Centre project. Before we get underway, I'd just like to introduce the members of the team. Jeremy Lever who was the landscape architect of the project; Wendy Pitts is the project manager for the contractor Mowlems Management; Anthony Field AYH Partnership; Chris Baxter, R.W. Gregory, the service engineers; Gerald Stone AYH Health, project managers; Andrew Mason, Powell Moya Partnership, project architect; and Ian Menzies, Charles Weiss Partnership, the structural engineers; and myself Roger Burr, Powell Moya Partnership, I was the director in charge. The building is a centre for the diagnosis and treatment of cancer. The client in fact was a double-headed client: the South East Thames Regional Health Authority, the principal client, and they worked with the Maidstone Health Authority to procure the Oncology Centre. The main requirements of the project at the time were related to the shortest time-scale to bring the centre on-stream in 1993, at the same time using the most advanced equipment for the centre both for treatment and diagnostic purposes, often computer driven technologies. The design team as a whole had in fact been gathered together some years beforehand, toward the end of the completion of the main hospital on the site, the Maidstone District General Hospital, and in fact there had been a hiatus of several years whilst the National Health Service reconsidered the criteria for treatment centres, radiotherapy centres, in the country as a whole. The result of this review ended up with a certain number of units in the whole country, and one for the South East Region was designated to be at Maidstone. It's an independent unit although it receives some support from the existing hospital on the site. The basis of the design team was drawn from the original group that completed the Maidstone District Hospital which was a new hospital completed about ten years ago on the site, in fact by the same contractor, Mowlems, the same architect, Powell Moya Partnership, the same engineers, Charles Weiss Partnership. But for the Mid-Kent Centre there had been a change. The client had their own engineering department which they kept for the Oncology Centre, and they also brought in their own project managers, who were then called Project Management Services, to help manage the whole scheme from the client point of view.





2


Site Plan

©Powell Moya Partnership


RB: The constraints to the design of the building emanated from its need to connect to the existing hospital on the site. It actually fulfilled the ultimate phase of development in that direction of the hospital. There were particular aspects in terms of landscaping and there was also the difficulty of dealing with a rising ground level which meant that the new building connected to the existing building by a bridge component. The client, under the auspices of the project manager, had spent some time developing a detailed brief which covered not only the policies but the various departments of the building that involved every single room, every piece of engineering in that room, and every element of equipment. The process of developing the brief came about through the interaction of a project team which was a team assembled on the client side involving users, the financial people, the administrators and, on the design team side, which involved the work's professionals. They met on a regular basis, developing the design, and ensuring every aspect of the detailed brief met with the users' very particular requirements.





3


Plan Of Centre

©Powell Moya Partnership


RB: The basic design approach was very simple. The centre was divided into three component parts: the first and largest was the treatment block; the second was the nursing section, the inpatient part, the care part; and the third was an independent service building which provided all the necessary support for this development. The treatment of the three components related to their relationship to the existing hospital to some degree. The nursing section was developed as an extension of the existing hospital and it connected by a bridge to the new treatment centre. The basic form of the treatment centre was devised around a courtyard space. The purpose here was to control two objectives: firstly to provide a very simple circulation pattern around the treatment block, that there was a clear and obvious movement for outpatients, people risking treatment, or people waiting to receive treatment; and secondly, as a space, presented a visitor with an optimistic and positive view, flooding the interior with daylight and celebrating some of the more positive aspects of light, water, plants and a pleasant outlook. GS: The client placed great emphasis to the whole of the design team on the need for a user-friendly building. Cancer patients are probably the most traumatised the NHS [National Health Service] treats. And, as a result of that, the need to make the building - particularly where it actually interfaced with the public front - a very soft, welcoming, friendly, optimistic atmosphere, was considered a high priority by the client, and moneys were allocated specially to fulfil this need. RB: Thank you Gerald for providing the client's point of view on the design approach. The development of the design process started with the appointment of the project managers at the very outset of the scheme. Following that, the design team members set to work and they in turn brought in further consultants; that was the landscape architect and the interior designer. There were also significant technical inputs that started at the very beginning of the detailed briefing process; that was on the science side, the scientific officer whose principal task was to fee into the design team all the necessary aspects of design for radiation protection, the use and handling of difficult materials and of very particular relationships and functions and their physical requirements. At the same time the fire officer was another important formulator of the detailed design aspects and the local fire brigade were part of this detailed consultation that occurred at that period. Yes Gerald, were there other consultants? GS: Not so much other consultants. But it's worth pointing out that the client specified that the building should be designed to take any equipment, rather than just that that was specified for it in terms of the specialist equipment, that is.





4


Linear Accelerator Enclosure. Axonometric & Plan

©Powell Moya Partnership


GS: The fact that the bunkers, the linear accelerator bunkers, were designed to take any linear accelerator currently on the market is significant because of the need to provide services to feed all and any sort of equipment that was put in there. RB: Thanks Gerald. It was the desire of the client to keep open his ability to select up-to-the-minute technology and also to be able to respond to rapid changes that were occurring in the diagnosis and treatment in this area, and we'll come on to see how that was organised by the project manager and the design team as a whole. In terms of town planning aspects, the nature of the development was not critical. The hospital sat in its own grounds, and there were no significant urban design relationships beyond that which was set up in the campus itself. I think now I would like to expand this discussion into the more detailed aspects and look at some of the more specific contributions of the consultants. I'd like to introduce Ian Menzies to give a more detailed explanation of the structural engineer's contribution.





5


Long Section

©Powell Moya Partnership


IM: Thank you very much Roger. There were two fundamental problems to be solved in the structural engineering context. The first was one that was well known from the involvement we had with the previous main hospital project and that was because of the underlying nature of the site. Because of the way in which the underlying chalk is folded, the area of Barming on which the hospital is located is notorious for the unpredictable appearance of what are called "swallow-holes", where the surface of the ground suddenly vanishes from underneath one's feet. We overcame this potential problem on the main hospital by constructing the foundations as a thick, one meter approximately thick raft which was capable, should such an event occur, of spanning a swallow-hole of up to approximately six metres in diameter. And it was decided, after looking at one or two alternatives, that this was still the most appropriate foundation system to adopt for the Oncology Centre. RB: And not only did it help solve the structural engineer's problem but this approach gave great benefits and opportunities by introducing an interstitial layer between the foundation and the actual used slab where we could run drainage and facilitate that part of the works.





6


Progress View From Road

©Powell Moya Partnership


IM: Thank you Roger. The second problem from the engineer's point of view was of the shielding, shielding from radiation escape within both the high and the medium energy linear accelerator units. This involved very considerable discussion with the Health Department's physicist in order to ascertain the fundamental physics requirements of this. The most cost-effective solution was to utilise dense reinforced concrete to form the shielding, and this necessitated walls of up to one metre in thickness, and the roof slab over the high energy accelerator of excess of two and a half metres in thickness. So it was a very considerable logistical exercise to construct that. GS: Could I just say that it wasn't the Health Department's physicist, it was the region's physicist. IM: Yes, I used the wrong term; I should have said the Regional Health Authority. WP: The walls are two and a half metres as well as the roof.





7


Service Block

©John Peck & Jo Reid


RB: The other probably significant element of course are the services in terms of the project. They constitute getting on for half the actual value of the works and in this particular context the nature of the equipment of course was complex requiring special conditions, and I'd like Chris to elaborate a bit further on the services components. CB: Like Ian, we had a number of problems to solve quite significantly, to do particularly with the radiation protection part. If you can imagine that these bunkers are completely surrounded in concrete, we therefore had a fundamental problem as to how to bring services into those rooms, both electrical services, mechanical services, air-conditioning, ventilation, and every other aspect that is required. We did very careful co-ordination with the building and the structure as it was actually created, and necessitated a lot of work to do with builders' work early on in the contract to ensure that these routes were left open to enable services to be brought in at a later date. The other fundamental problem we also had to get over, which Gerald already touched on, which is to do with the client requirement for a domestic or hotel type environment to the building, was to always try to ensure that services remained unobtrusive, was always in sympathy with the architecture of the building. All of these services were derived from the service centre which is effectively built at the end of the project. We did in fact take a number of primary services all the way across the route of the building on an upper level street. These services were terminated in the service centre. Like a lot of hospitals, an underground subway was created between the centre and the treatment block. RB: I think one might say here that the approach to the design of the services, or the design of the centre, was really to only be dependent on artificially-supported environments where there was an actual or clinical or technical need. Generally speaking, the rest of the Centre and of the nursing sections were as naturally ventilated as they could be. CB: That's true to a large extent. Certainly, the treatment block with its specialist rooms with simulator machines and linear accelerator machines all required reasonably close control ventilation systems. RB: Could you just perhaps mention the energy-saving aspects of the design, any particular measures... CB: Really two measures were taken in particular for energy-saving purposes. Most of the air-handling units which provided mechanical ventilation for the treatment block were provided with heat-recovery coils from the extract systems, and considerable use of low-energy lighting fittings were used throughout the development as well. So in that respect there was a considerable amount of energy saving in the building. Typically, hospitals are not easy to do this with. RB: We did of course have a highly insulated envelope and the whole system was actually sort of plugged into the building management system for the whole of the hospital complex. Another, of course, very important contribution here was the quantity surveyor [QS] who helped establish and manage the control of costs. And perhaps Anthony Field would like to elaborate further. AF: Our main problem was coming in after the other consultants dealing with various problems that they have, and doing cost analysis, seeing which is the best way around or over these problems, fitting in briefly with the client's requirements and obtaining a budget that the client is happy with. AR: Could you elaborate perhaps on the establishment of a cost plan in order to shape and help regulate the design process and subsequent interventions? AF: The cost plan is established on how many people are due to come into this hospital, how many beds you've got; and then, on top of that, you get what they call an 'on cost' which is the cost of actually making this system work, how hospitals work. On this scheme it's very high because a lot of the accommodation provided was not standard, very exclusive to this project. Once you've got this budget set up, we then developed this in consultation with all the other consultants. They would get feedback from all consultants, adjust money as necessary and cost control against each element, setting up budgets, targets of which each element has to be designed to; and it's a very good process of which to report back to a client, showing where perhaps you need more money or you don't need so much money. It's very much a two-way exercise.





8


Landscape Plan

©John Peck & Jo Reid


RB: Thanks Anthony. Part of the other design inputs were on the landscape design and interiors and Jeremy Lever will tell us a little bit more about the landscape approach. JL: Basically, when I joined the team the first thing I had to do was do an appraisal of the surrounding areas because the building was not to stand in isolation. But the only elements, strong elements that one could relate to, were two small woodlands on the northern boundary. They were coppice and sweet chestnuts, namely they would be cut down every seven years, a seven year cycle, so it was not a permanent feature. But what was very clear was the degree of exposure of the future buildings, and the existing ones for that matter, from the strong north and north-east winds; there was no shelter-belt planting to reduce the velocity of these winds. So that was one of the first things that one realised, one would have to establish a strong sense of the terminal to the landscape because the service station is the most northern element. In landscape terms, I had to respond to this situation by forming a link between the existing landscape and this group of buildings.





9


Inner Courtyards

©Powell Moya Partnership


JL: Another aspect of it was to give clarity to the building form, both for pedestrians and drivers. The other thing of course, one had to have a sense of response to the needs of the patients, staff and visitors when designing the three courtyards. So in general terms, there is the bigger area, the surrounding area, the way in which one is going to bind the buildings into the local landscape.





10


Inner Courtyards

©John Peck & Jo Reid


JL: There was the protective aspects of it from the weather conditions, and there was the thing of giving clarity and understanding for people approaching the buildings. RB: Thanks Jeremy. The interior design was perhaps the final element that came together in this detailed interaction. John Haddock in fact was the designer here. He worked in conjunction with the architects and the design team, developing an interior scheme reflecting the client's desire to have an ambience centre. The main reception and circulation areas - I think as we mentioned before - had deliberately a greater slice of the budget to enhance their finishes. There was a combination of the use of natural finishes, timber veneers, timber to soften the otherwise more clinical nature of the unit; a high dependence on the natural lighting which meant that there was a use of bold colour, but one not to stimulate but rather to calm, and blues and more neutral greys.





11


Consulting Room

©John Peck & Jo Reid


RB: The technical aspects of interior design also involved specialist testing materials to ensure that they weren't absorbent to electrons and could have any radioactive carry-over; also other materials had to make sure they weren't likely to fade under radio-active exposure; and of course the ever-present requirement to be clinically sound, i.e. not leading to the growth of infections or bacteria. So there was off the scene testing going on all the time of the initial selections of materials and finishes. In the end these were all brought together, as was the whole of the design, to make various presentations to the client groups to get final approval to the whole project.





12


Progress Photo

©Powell Moya Partnership


RB: Perhaps at this time one might move on to see how the project was procured, because it had particular problems. We've mentioned how the actual centre was in three parts, the service centre, the treatment block with its front door flying canopy, and then the in-patient part which was actually more an extension to the existing building. There were in fact two further problems: one was the need to increase the size or the capacity of the present kitchen in the hospital which was going to serve patients; and the other was the need to increase the capacity of the mortuary. These were both difficult problems because they were part of the existing hospital, which would mean that work would have to occur within that existing situation, and they had to come on-stream in readiness for the treatment block, in readiness for the new centre, so they'd have to be in advance. There were also the problems to deal with the interfaces of the nursing section where it actually is physically connected to the existing hospital, and there would be problems there of maintaining the nursing sections without disrupting patients, staff and the general running of the existing hospital. So there were all these difficulties. There was also the need to keep open for the client the opportunity to respond and react to changing treatments and advances in technology. So a decision was made at a very early stage on a particular method of procurement, and I'd like here for Gerald, the project manager, to introduce the basis behind that selection. Perhaps we could expand that to include other members of the team. Gerald, perhaps you could talk about the nature of the contract, the type of contract. GS: The type of contract chosen to procure the Oncology Centre is a JCT87 management contract. This was somewhat revolutionary for the client to consider. It was the first of the sort they'd ever done. The main purpose of using such a contract was a keenness on the part of the client to see work started on site at an early date, so that credibility could be given to the project as a whole as it had been in the planning stages prior to this team's establishment. JCT contract is a variation of the standard form of contract that splits the building of the contract into individual contracts for its component parts. RB: Yes, but I think one of the first sort of benefits that the type of contract would give the team and the client was the ability to bring the contractor on at a very early stage and before, in fact, we'd completed all our detailed design work. And it also meant that, by having the contractor on board so early and part of that development process, that should there be a need for any change on a technological or even a planning change within the building, we would be more readily and more easily able to achieve that without incurring what might otherwise have been severe financial penalties or time penalties in a more conventional type of contract. It was quite unique for this client to use a flexible approach in that way and we'll come onto some of the issues that came from that. Perhaps, Andrew, you might like to expand on how we actually chose the contractor, having decided on a method.





13


Progress Photo

©Powell Moya Partnership


AM: I think one ought to explain to those who are not 'au fait' with contracts, that a management contract is where the client employs the contractor to manage the project on his behalf and the contractor does not actually construct the work. And therefore it enables the contractor to become a member of the team, and therefore procure building speedily and without delays to the project. AF: I think it should be said that the adoption of a management contract also enabled the client to respond, through the design, to any changes in cost that were received as packages were returned. Also, I think it should be said, as this was a revolutionary procurement method for an authority, and because the Health Authority was a little bit concerned about the risk he was taking, amendments were made to the standard contract which enabled him, if the costs were becoming a problem to him, to stop the job and re-think the situation, thus reducing the client's risk. RB: Thanks Anthony. Shall we just look at how the contractor was selected to run with that form of contract, because they became a very important part of the process? Andrew, I know you were involved in that selection procedure; perhaps you could briefly outline what happened. AM: Clearly a number of contractors were aware of the project going forward and had approached our client to be considered, and a short list was drawn up for the number of major contractors with management experience that we felt were able to carry out this fast track program. Each contractor was given an opportunity to give a presentation to the design team and the client to ensure that we were happy with the quality of the contractor to be put forward for a fee bid. Fee bids were invited and we were happy to run with Mowlem's who had a wealth of experience, having worked on the original site. RB: I think this might be an appropriate moment, Andrew, to ask Wendy to add her views on this appointment, in fact how quickly did Mowlem get involved and their first contacts with the design team. WP: John Mowlem Construction became involved with the project in May 1990 and initially were employed for pre-commencement services after four weeks. Unfortunately the client had funding problems in another area and the job was stopped. So, in conjunction with AYW, we formulated a number of options to go forward in terms of funding and timing to allow the job to continue; and the client accepted one of these options and then we re-started work in pre-commencement in October 1990 which was six months before construction actually began. This allowed us to be involved, with all the design team, with the design process, giving our advice on 'buildability' of the project, and also to put together the works packages. We commenced initially with the refurbishment of the mortuary and the refurbishment of the kitchen in February 1991 and work commenced on the construction of the Oncology Centre on March 4, 1991.





14


Management Control Plan

©Powell Moya Partnership


RB: I'd like just to elaborate a little bit more on the notion of the concept of packages in relation to the management contract, how they were generally used in its organisation. Perhaps Wendy you could elaborate further on that. WP: As a management contractor, we're employed to manage the contract. Therefore we put a team of supervisors and professionals on site to manage the construction process. We don't actually do the construction work ourselves. For this we employ works package contractors, and in the case of Mid-Kent Oncology, those works package contractors were employed on an elemental basis, i.e. we had superstructure packages, we had mechanical packages, electrical packages, all in all we had thirty seven different works package contractors, and those were chosen in consultation with the design team. We put together the list of the elements that we wanted to go to, and they were procured at the early stages of the project. And this ensured that one could start procuring earlier packages as the design for later packages was being completed. RB: Great. Perhaps, Anthony, you might like to comment here on how the client's risk or exposure to a contract, where he didn't know quite where all the packages were at one time, what sort of money he'd be in for, how that was controlled. AF: We procured the mechanical and electrical packages fairly early, as these had nearly fifty percent of the total value. So that the majority of the financial outcome was known at an early stage, and a clause was written into the contract that the client had the right, when sixty percent of the packages had been built, that you could stop the job if it was deemed necessary due to financial reasons. This reduced the client's risk substantially. RB: It was a very useful safeguard from the client's point of view. Generally speaking the work started off in a very orderly way and proceeded diligently. But as time went by, things happened. One of the major sub-contractors fell into trouble and went bankrupt during the works. What actually happened and how important was it? WP: It was very important and it had a fundamental effect on the completion of the project. In employing works package contractors, at the short list stage we do financial checks on all of the short list candidates; and in particular in mechanical and electrical work, because they represented a large proportion of the project. Our accountant actually checked the books, the current trading books, for both the mechanical and the electrical sub-contractors. Unfortunately, in a recessionary time they can have perfectly good trading facilities at the start of a project.





15


Services Into Wall In Progress

©Powell Moya Partnership


WP: The electrical contractor actually went into receivership in June 1992, the worst possible time in the construction of the project. The most critical time in the construction of the hospital is the time between putting up the studwork and completion of the installation of services into the wall - mechanical, electrical and plumbing services plus all of the nogging that take fittings that go on the wall afterwards. Unfortunately the electrical contractor went into receivership almost halfway through the first fix activity which meant that effectively the entire job could possibly have come to a complete standstill. We put matters in hand very quickly to try to overcome this. We directly employed a small number of electricians on site to enable some work to continue and to allow some continuity for following works contractors. And at the same time we entered into negotiation with the mechanical contractor to get a price to complete the project and he commenced work at the beginning of August to complete the project. There was a delay of eleven weeks. However it is reasonable to say that within that time we also accommodated a large number of additional elements. GS: On the question of the programme, although the completion of the project was later than Mowlem's original contract completion date, it was still within the time that the client had originally envisaged for the project to be completed and was in accordance with his own commissioned programme.





16


Linear Accelerator Being Built

©Powell Moya Partnership


RG: Another important operation which occurred in the contract, which was foreseen but nonetheless equally difficult and complex, related to the construction of the linear accelerator room with the high tech equipment. We referred to them earlier. In fact Ian would like to talk a little bit more about the actual construction of these. IM: The construction of these particular rooms involved the placing of very thick concrete elements both in walls and in roofs. The formation of construction joints within these walls were to have provided a possible path for radiation to escape beyond the shielding. Similarly the formation of the normal shrinkage cracking that usually occurs in very thick concrete sections, were again to provide possible escape routes for radiation. Both of these eventualities were avoided. The courses of action which were adopted were, one, to replace seventy percent of the cement content of the concrete mix with ground, granulated blast-furnace slag in order to reduce the heat production that inevitably occurs as concrete sets, it's an exothermic process. And the second very innovative move which was taken in conjunction with Mowlem's management contractor and with the package concrete contractor was to specify that the concrete had to be placed at a temperature not in excess of ten degrees centigrade. In order to achieve that, the concrete, while it was being placed, had to be cooled by injecting liquid nitrogen into it. This was highly effective; the finished product has been very successful and, so far as one can tell from the visual inspection and from the radiation testing that was carried out, it has been totally successful in eliminating both construction joints and shrinkage cracking. It wasn't the first time it had been done but it was certainly a very new process. It involved placing in one continuous pour something like three hundred and seventy five cubic metres of concrete, which is quite a logistic exercise on its own. WP: The works were undertaken by PC Harrington and we were fortunate that ARC and ECG (the concrete manufacturers and British Oxygen Co.) were very keen to promote this form of construction and therefore very helpful in the design of the mix and in the process of actually doing the work. The pour took thirteen hours pouring time. It was quite a logistical problem and I think they coped very well with it. And I think the result is concrete of an extremely high quality, and in fact probably the best finish of concrete that one has seen for quite a while. RB: Gerald, during the course of the development of the design, and indeed to some extent on site, there were changes that occurred at the client end. Perhaps could you elaborate on those? GS: Yes of course, Roger. Mention was made earlier of the requirement of the funding of the job, that the job had to be put on hold for about six months. And whilst obviously various options for considering how the payment would be carried forward, time was also used fruitfully to re-examine the content of the building. The treatment of cancer sufferers is very much a leading edge technology and there are many new processes for easing the suffering of the patients that have been developed. Opportunity was taken to incorporate some of these facilities into the new building as the design had effectively been stopped; the design process had been stopped. And whilst it was felt that it would be disruptive to change the layouts of the functional contents at this late stage, it was considered advisable, if the centre was to perform its role as one of the finest centres in Europe, that these sort of facilities were included. Certain innovative designs were drawn up, especially for part of the treatment which is called Brachytherapy which doesn't involve deep layer radiation, but rather more the surgical implanting of elements that then are radiated whilst the patient is being kept in the supine position. What the effect on the patient is that, instead of having to lie absolutely immobile for four or five days, the treatment can be concluded in something like twenty minutes with quite minimal after-effects both medically and psychologically. The help of the region's physicist was enlisted by the designers to provide daylight in some of these rooms. And this, as far as I am aware, is unique in any centre of this sort.





17


Radiation Shield Around Courtyard In Treatment Section

©Powell Moya Partnership


GS: This was done by the expedient of providing radiation-shielding walls outside the very large windows which enabled the patient to feel much more human, inasmuch as he can see what daylight is doing, he can see out into the outside world. Perhaps, Jeremy, you can elaborate further on this too. JL: Yes. This I think was one of the best decisions from my point of view. Providing a window obviously is brilliant for the patient. Also it gave me a chance to think about what one may place inside the shield wall. A shield is really, one feels, is keeping something out. This is keeping the radiation in. And so the curved shape in the form of a coil winding up was providing shelter for the rooms and people working outside, as well as forming not too oppressive an enclosure. Because the difficulty was that, since it radiates out from the position of the patient, in the same way, one might say, that patient at low-level would not be able to see out. If one could bring a bit of the garden inside, it would make the patient realise that the patient is not so trapped within. And to this end, one was able to introduce a tree, a Gleditsia, which gives a feeling the sun is on it. These shields were providing a lot of shade as well, and it's quite nice if one gives a feeling of the sun is out, and on this tree in actual fact is a yellowish leaf and gives that nice glow within the rooms. Also, the chance to bring in other materials, which maybe sounds a bit pretentious, but if one produces a series of boulders and rocks and things like that, and plants, there is a feeling of season and longevity and so on. So, trying to associate those sorts of feelings with this very small space, one was attempting to improve the lot of the patient.





18


Medium Linear Accelerator Room

©John Peck & Jo Reid


CB: I think the second and possibly more fundamental change that was made to the project, as the project evolved, was the proliferation of the computer equipment within the building itself. When we completed the initial brief for the job, the room specification sheets contained nothing more than a requirement for a computer outlet and then not in every location. As the project evolved and the sophistication of the treatment and management facilities of the centre became more and more known, it was quite obvious that this initial provision was by no stretch of the imagination sufficient for the uses to which the building was to be put. Subsequently, a complete reassessment of what computer systems would be likely to be required was made, which caused immense headaches for the design team to try to incorporate. Computers were being used for such things as the verification recording and management of the computer systems that controlled the treatment machinery. They were being used to transfer images digitally between various parts of the centre and various satellite centres scattered around the south east of England.





19


Link To Main Hospital

©Powell Moya Partnership


GS: There was a need for a connection to the hospital's management system which unfortunately, as far as the centre was concerned, was not actually in existence when we started to design the computer systems themselves. There were also a number of other interfacing computer systems and all of these required a huge input, from the services engineers particularly. Perhaps Chris could elaborate on how we overcame some of the problems. CB: Certainly. In principle a lot of the additional computer equipment to be installed in the building was in the control rooms and the control areas which adjoin the specific treatment rooms. All of these areas were totally redesigned, not only by ourselves but the architects, to ensure the provision was there for now and the future to uphold a considerable amount of up-grading of computer systems, software and hardware. This meant mainly including a vast amount of additional internal carcassing and trunking systems and power systems to up rate what had already been included for, which, as Gerald has already said, was totally inadequate. In addition to this, because there were so many links to various other areas within the Oncology Centre and the hospital, we also had to get involved in providing additional carcassing system at the roof level to transport local area network systems throughout the rest of the building. This was done at the time - correct me if I'm wrong, Wendy - where a lot of ceilings were already up in various areas and this involved an additional amount of time for the contractors to sort out how to programme around where they were trying to finish, and yet maintain a substantial sort of variation in carcassing the services. Additionally, we established I think three computer hub network rooms which needed enhanced air-conditioning and certainly enhanced power sources as well, and these were taken on board in an individual way, whereas all of the building was air-conditioned by a central plant. This now really necessitated a split system of air-conditioning units being installed in the separate rooms because we were far too far down the line, with other major equipment, to change it.





20


A Treatment Room

©Powell Moya Partnership


RB: Thanks. I think one of the features generally of the project was - once we had dealt with the patients and their requirements - one of the other key factors was the equipment, much of which was extremely expensive and sophisticated. We've mentioned the construction of the enclosures or the rooms that house the linear accelerators, but the actual procurement of those machines was one of the guiding factors in the development of the whole project, since they constituted a great financial commitment and a technological commitment. I think, Wendy, would you like to expand on the requirement to bring these spaces on early, so that the client would have the opportunity of commissioning them at the earliest opportunity in the project and how that impacted the organisation of the work. WP: Obviously in keeping with the fast track, there was the requirement to bring on the linear accelerator machine and some other machines at an early date, overlapping construction process. Because, although they take a relatively short time to actually install, from six to eight weeks, they take an inordinately long time to commission and get into correct working order. But to facilitate this, the linear accelerator bunker areas and other key areas were targeted for early completion, and those were completed by a certain set of dates and then they were effectively cordoned off to allow the installers to have direct access into those rooms.





21


Model Of Centre

©Powell Moya Partnership


RB: During the whole of the construction period, the design team as a whole were, of course, active, responding to these changing circumstances, despite the fact that the sketch scheme had been agreed and determined prior to the construction getting under way and the management contractor coming on board. As architects, we co-ordinated and monitored all these effects and changes, ensuring that the design principles that were established with the client and the user groups at the outset were being maintained and, where possible, enhanced. I think we mentioned earlier how, as the cost plan evolved, we could begin to identify that the nature of the market was allowing a greater opportunity to give better value for money for our client. We then started to produce proposals in consultation with them, seeking where possible to enhance some of the earlier specifications. Areas where this occurred were particularly related to the interiors.





22


Reception Area

©John Peck & Jo Reid


RB: The reception area where we used a rather unusual form of seating, a serpentine seating. A combination of beech natural wood upholstered furniture gave a very distinctive entrance to the unit; as such it was an enhanced feature, something we were able to do by responding rapidly to the opportunity offered by the cost plan.





23


Art Works Will Be Hung In This Corridor Joining Sub-Waiting Areas

©John Peck & Jo Reid


RB: In the same way we were able to develop a works of art programme for the building in conjunction with the client, looking to acknowledge sites, within the building and courtyards and places generally, where specific works could be commissioned. And that is actually now continuing as a process; two are already in place and others are planned. We'd now really like to summarise the extent of our discussions. A think probably the key things from our point of view - the people around the table - has been the nature of the teamwork involved on this project, the combination of the contractor working very closely as a member of the design team, responding directly and rapidly to a client who has very complicated and very specific needs, which in themselves do change quite quickly. It's interesting to note that even after the completion of the project, that change is still part of the unit.





24


A Canopy Marks Main Entrance

©John Peck & Jo Reid


RB: The job, despite its complexities and the problems we had to deal with, has been successful. It was completed within the overall timescale that was required and within the budget that was set. Since completion early this year, the whole unit has rapidly been fully commissioned, patients have now been in for some six months, and the final linear accelerator room is due for final commissioning at the end of December 1993. Since that time it's very gratifying for the team that the building has received a Royal Institute of British Architects Award which goes in some way, I think, to recognise the commitment of both client and the whole design team in the project. Before ending, I would like Gerald to summarise from the client's point of view of the project. GS: The client is delighted with the building and has said that he feels that the design was well thought through and sensitively executed. Facility in his view was impressive and has met all his expectations and will provide "the finest comprehensive cancer treatment centre in Europe". Mention has already been made of the treatment rooms where the windows are, the un-hospital-like atmosphere, the decorative lighting, the central courtyard, all of which enhance the feel of the building for the patients that it treats. The overall impression that the client has is that the building is most favourable and it's universally praised by both staff and patients. All of this is very gratifying for the team to know that the design has been appreciated by its ultimate users, which is not always the case in public sector life. But, in all truth, the building itself is generally thought of as a flagship in terms of National Health Service buildings and is being constantly visited by people to see how it should be done.